Indiana Office of Energy Giving Grant Funding to Community Energy Efficiency and Conservation Projects Memorial Hospital Announces its 2024 Scholarship Recipients Immersive Installation Exhibit by John Begley and Linda Erzinger at Thyen-Clark Cultural Center Indiana Recycling Market Development Program Proposals Now Being Accepted Fourteen Historic Preservation and Archaeology Grants to be Awarded by Indiana DNR

Weather permitting, the Jasper Street Dept. along with its contractor, RejuvTec, will begin Jasper’s next pavement preservation project on Thursday, July 19. This project will span over a several day period.

Residents along the affected streets will be notified with a door hanger & “No Parking” signs the day prior to work beginning on their street. All vehicles & traffic must be removed from the scheduled roadway no later than 7:00 A.M.  The contractor will close the street while applying the Reclamite treatment.  Sand will be applied to increase traction during absorption. No Traffic will be allowed on these streets until sand has been applied & the street has been cleared for traffic to flow, as the street will be slick & oil will adhere to vehicles.

Motorists need to keep speed at a minimum for several days following application of this process, as to prevent this substance from adhering to vehicles.

In the event of inclement weather or any other unforeseen events, the work schedule will be revised.

The following is a listing of scheduled streets for this project: (not necessarily done in this order)

400 W, S of Division Rd – from Division Rd to Lakeview Dr

Brescher Dr – from West of Evergreen Ln to 400 W

26thSt – from Newton St going E to the Dead End

Birk Dr – from 26thSt to Brosmer St

Portersville Rd – from 36thSt to 41stSt

Ann Ln – from Portersville Rd to West of City Limits

36thSt – from St Charles St to Hartford Dr

Manor Dr – from Overbrook Dr almost to 41stSt

Hartford Dr – from 36thnorth toward Leawood Dr

Reyling Dr – from Leslie Dr to Newton St

Gun Club Rd – from Crestwood Dr to East of City Limits

Dorbett St – from SR 56 north to 13thSt

S Meridian Rd – from 3rdAve to Decora box culvert

Terrace Ave, East – from Justin St east to Dead End

Terrace Ave, West – from Justin St to Brames Rd

41stSt – from Baden Strasse to Portersville Rd

Obing Strasse – from 44thSt to 47thSt

44thSt – from Baden Strasse just short of Downey

Worrell Dr – from 13thSt to 15thSt

Baden Strasse – from Newton St to Manheim Rd

Andrew Ln – from Kluemper to Truman Rd

The Jasper Street Department appreciates your patience during these projects for the upkeep of Jasper’s infrastructure.