The Jasper Street Department, in collaboration with contractor Calcar Paving, will begin milling operations on several streets starting Wednesday, September 11. The schedule for milling is as follows:
- Wednesday, September 11: Highland Street from 3rd Avenue to St. James Street, and St. Charles Street from State Road 56/6th Street to 300 feet south of this intersection.
- Thursday, September 12: Giesler Road from 3rd Avenue to Genevieve, Hopf Avenue from Justin Street to Brames Road, and Justin Street from 3rd Avenue to Schroeder/Maurice Streets.
- Friday, September 13: West 15th Street from Bartley to Kundek, West 10th Street from Carroll to the west end, and all of Edward Street.
Residents are advised to remove their vehicles from these streets by 7:00 a.m. on the respective days to avoid any inconvenience. Please note that the schedule is subject to change due to weather conditions or unforeseen delays.
Following the milling operations, the streets will be resurfaced during the week of September 16. The street department appreciates your cooperation and patience during this time.