Indiana Office of Energy Giving Grant Funding to Community Energy Efficiency and Conservation Projects Memorial Hospital Announces its 2024 Scholarship Recipients Immersive Installation Exhibit by John Begley and Linda Erzinger at Thyen-Clark Cultural Center Indiana Recycling Market Development Program Proposals Now Being Accepted Fourteen Historic Preservation and Archaeology Grants to be Awarded by Indiana DNR

The Jasper Street Dept along with their contractor, Calcar Paving will lead off the 2021 Milling/Paving season extending throughout the next 7 days, weather permitting.

Milling will begin Thursday & Friday, May 20 & 21st with Paving to follow Monday thru Wednesday, May 24 & 25th on the following streets:

Easy St.

Crossroads Ave.

University Dr. from Grandview, north to the cul-de-sac

Grandview Dr.

Hillbrook Dr.

Willow Ln.

Greene St. from 13thto 15th

Anderson St.  from 4th to 8th

6th St. from Anderson, east to RR crossing

Paver patch on 6th St in front of JPD

(The milling/paving will not necessarily follow the list above.)

Motorists may wish to avoid these areas, as although these streets will not be closed, there will, however, be delays.

Again, this schedule will be followed, barring inclement weather or any other unforeseen events.