Santa Claus Breaks Ground on 44-Unit Frosty Falls Housing Development Phone Scam Circulating in Perry County Daviess Community Hospital Welcomes Tanisha Chamberlain to Hospitalist Team Tell City Releases Adjusted Holiday Trash Schedule Gibson County Deputy Assists With Roadside Birth at Haubstadt Truck Stop

JASPER PAVING
Officials with the City of Jasper say now that the milling process is complete, the Jasper Street Department along with contractor, JH Rudolph, will be paving streets that were milled last week, however due to a scheduling conflict, paving has been moved to next week.

The street department says the paving schedule has been changed to next Monday, Tuesday & Wednesday, October 3rd, 4th & October 5th. They say the scdedule of Streets remain the same with Terrace Avenue in the Holy Family area in its entirety being covered as well as Worrell Drive near Jasper High School.

Also, 41st St from Portersville Road to Baden Strasse,

44th Street from Obing Strasse to Baden Strasse,

Obing Strasse, in its entirety,

And the intersection of Baden Strasse & Manneheim Road at US highway 231 all on the city’s northside.

Motorists are asked to slow down and use caution while approaching and driving through work zone areas. Any questions, contact the Jasper Street Department at 812-482-1130.